On January 16, 2025, FERC approved a contested settlement agreement and rate schedule governing the provision of reliability must-run (“RMR”) service from the Indian River Unit 4 generating facility (“Unit 4”) in PJM...more
On November 21, 2024, FERC issued an Order partially accepting NorthWestern Energy Corporation’s (“NorthWestern”) compliance filing, effective July 10, 2024. FERC found that NorthWestern’s filing partially complies with the...more
On September 10, 2024, FERC issued an Order denying two complaints. The first complaint was filed on January 23, 2023 by Montana-Dakota Utilities Company (“MDU”) against Midcontinent Independent System Operator, Inc....more
On April 25, 2024, FERC approved the California Independent System Operator Corporation’s (“CAISO”) request to increase its capacity procurement mechanism (“CPM”) soft cap offer from $6.31/kW-month to $7.32, which will become...more
On March 21, 2024, FERC issued a Notice of Inquiry (“NOI”) seeking additional information on whether the Commission should continue to allow interstate pipelines to package “high value” capacity with non-contiguous and...more
4/8/2024
/ Climate Change ,
Comment Period ,
Energy Policy ,
Energy Projects ,
FERC ,
Greenhouse Gas Emissions ,
Infrastructure ,
Natural Gas ,
Notice of Inquiry ,
Oil & Gas ,
Pipelines ,
Regulatory Agenda
On March 21, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 2023-A (Final Rule), which reaffirmed aspects of Order No. 2023 — the Commission’s landmark order updating its generator...more
On December 19, 2023, the U.S. Court of Appeals for the Sixth Circuit (“Sixth Circuit”), in Electric Power Supply Association; PJM Power Providers Group v. FERC, held that the former Chair of the Federal Energy Regulatory...more