Latest Posts › Construction Industry

Share:

Construction Projects: Issues with Cost Estimates

The cost of construction materials has risen like never before. This, in turn, creates pressure for parties to use cost estimates and budgets rather than "fixed price" contracts. Providing cost estimates can therefore be...more

Invalid payment claims and notices under construction contracts

A key part of the interim payment process in construction projects is the issuing of payment notices by payee and payer alike. Two recent UK cases demonstrate a strict approach being taken by the courts to the validity of...more

Construction contracts: extensions of time and apportionment of delay

If an extension of time (EOT) clause permits the apportionment of delay, what should be taken into account when apportioning delay? Comments in a recent decision of the Singapore Court of Appeal indicate that a party's...more

Extensions of time in construction projects: prospective or retrospective delay analysis?

Contractors' extension of time (EOT) entitlements and associated financial rights are always to be assessed pursuant to the applicable contract mechanism. A recurring question is whether EOT entitlements are to be determined...more

Construction Contracts: Liquidated Damages Recoverable for Period Prior to Termination

In Triple Point Technology v PTT, the Supreme Court of the United Kingdom has restored the orthodox position on how termination prior to completion of work affects the operation of a liquidated damages...more

Transformation in the construction industry: Keeping pace with change

[co-authors: Rhulani Matsimbi, and Kit Goodfellow] Three pillars are at the heart of global efforts to boost sustainability and make our built environment cleaner, greener and more socially responsible: construction,...more

Time-bar clause in construction contract defeated by estoppel

Estoppel and waiver are common arguments used to rebut the enforcement of time bar and notice provisions in construction contracts. However, these arguments have often seen limited success. Nevertheless, estoppel was...more

Multi-tiered dispute resolution: the use of conciliation

In the UK, disputes in the construction industry are rarely resolved through conciliation, with parties preferring recourse to adjudication, mediation, litigation or arbitration. However, a recent Australian case highlights...more

Oral variations: "My word is my bond"?

Variation powers under construction contracts typically contemplate work being authorised as a variation where it is instructed in writing. This can give rise to disputes over whether work is a "variation" if it is instructed...more

Construction contracts: who bears the risk of cost overruns?

Construction contracts may be priced in a number of ways. For most contracts, even those which are "fixed price", there is usually scope for cost/price variability. Four cases from December 2020 highlight some of the...more

Time bar notices: specifying the contractual basis of claim

Can a valid claim notice issued, on time, referring to one contractual basis, be relied upon where a claim is ultimately pursued on a different ground? In the first authoritative case to consider this issue, the Hong Kong...more

Compelling the performance of construction works

Courts and arbitral tribunals in many jurisdictions have the power to order contractors to perform building works - to order "specific performance" of a construction contract.  But these powers are rarely exercised.  A recent...more

Termination For Insolvency in Construction Contracts

Recent insolvency law reforms in the UK, Singapore and Australia impact upon the ability of a party to a construction contract to terminate it due to the other party's insolvency... ...more

Descoping: Can the omission of works constitute a breach of contract?

A recent Scottish case considers the contractual power to omit works and highlights key principles applicable to the question of whether omitted works can be transferred to another contractor - The descoping or omission of...more

Claims For Liquidated Damages Against Subcontractors

Main contractors often make claims against subcontractors for liquidated damages for delay. A question that sometimes arises is whether liquidated damages may be claimed by a main contractor where there is no corresponding...more

Advance payment guarantees: three unsuccessful attempts to prevent encashment

Advance payment guarantees are commonly used in the construction industry. However, successful challenges to a demand made under an advance payment guarantee appear to be less common. This article looks at three recent cases...more

Shifting foundations: amendments to ground conditions clauses

Amending standard forms of construction and engineering contracts to change the risk level between the parties is a perennial issue. This, however, can lead to disputes due to amendments not clearly reflecting the intention...more

Subcontracting without consent – when performance gets personal

Restrictions on a contractor's rights to subcontract works are common across industry forms of contract, and breach of these provisions can have significant consequences for a contractor. In a recent Australian case, the...more

Disputes between members of a construction joint venture

The case of Doosan Enpure Limited v Interserve Construction Limited represents a rare consideration by the English High Court of a dispute between members of a construction joint venture. The court found that Interserve was...more

Turning off auto-correct? Employers' ability to recover costs of correcting contractors' defects

In Thio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175 the High Court of Singapore confirmed that an employer may recover damages for rectifying defects even when it has done so in breach of a contractual defects...more

Construction contracts: "No damage for delay" clause enforced

In a recent case, the Federal Court of Australia confirmed that it will enforce a "no damage for delay" clause, including when delay occurs as a result of a variation under a contract....more

Security of payment: claiming a sum that “may” be due?

A recent decision by Singapore's highest court has held that a contractor must first establish that it is entitled to payment under the contract in order to claim progress payments under the Security of Payment Act, raising...more

22 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide