D.C. Circuit upholds FERC orders granting natural gas pipeline companies’ requests to extend project deadlines.

The United States Court of Appeals for the District of Columbia (“D.C. Circuit”) recently upheld two FERC orders granting natural gas pipeline developers’ requests to extend their construction deadlines. The D.C. Circuit...more

FERC Initiates Inquiry into Capacity Allocation on Non-Contiguous Pipeline Segments

On March 21, 2024, FERC issued a Notice of Inquiry (“NOI”) seeking additional information on whether the Commission should continue to allow interstate pipelines to package “high value” capacity with non-contiguous and...more

DOE Proposes to Limit NEPA Review for Transmission, Storage, and Solar

On November 16, 2023, the U.S. Department of Energy (“DOE”) issued a Notice of Proposed Rulemaking (“NOPR”) to update its National Environmental Policy Act (“NEPA”) implementing regulations to add a categorical exclusion for...more

Troutman Pepper Summary of FERC Order No. 2023 on Generator Interconnection Reform

On July 28, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 2023 (Order No. 2023 or Final Rule), which updates the procedures for interconnecting large generating facilities (20MW and above)...more

FERC Overhauls Existing Pipeline Project Analysis, Creates Separate Interim GHG Policy for Gas Infrastructure Projects.

On February 18, 2022, FERC issued two new, significant policies governing how FERC will review proposals for new natural gas pipeline projects (see February 18, 2022, Troutman Pepper Insight). Headlining these policies is...more

FERC Overhauls Existing Pipeline Project Analysis, Creates Separate Interim GHG Policy for Gas Infrastructure Projects

On February 17, the Federal Energy Regulatory Commission (FERC or Commission) announced two new, significant policies that may have a profound impact on both natural gas pipeline projects before the Commission and the...more

D.C. Circuit Grants Emergency Petition for Stay of FERC’s Order Terminating Killingly Energy Center’s ISO-NE Capacity Commitments

On February 4, 2022, the United States Court of Appeals for the District of Columbia Circuit (“DC Circuit”) issued a per curiam order granting NTE Connecticut, LLC’s (“NTE”) petition for issuance of a writ under the All Writs...more

FERC Announces New Policy on Interventions in Extension of Time Proceedings for Gas Pipeline Certificates

On January 20, 2022, FERC granted Adelphia Gateway, LLC’s (“Adelphia”) request for an 18-month extension of time, until June 20, 2023, to construct and place into service the proposed Adelphia Gateway Project. The order also...more

FERC Revises Policy on Authorizing Pipelines to Commence Construction Pending Requests for Rehearing of Certificate Orders

On May 4, 2021, FERC issued Order No. 871-B, clarifying that the rule established in Order No. 871, which precludes FERC from authorizing natural gas pipeline companies to proceed with construction of approved pipeline...more

Mountain Valley Pipeline Construction to Resume over Opposition from Chairman Glick and Commissioner Clements

On March 24, 2021, FERC modified a December 17, 2020 order (“December Order”) while reaching the same overall result, allowing construction to recommence for a portion of the Mountain Valley Pipeline, LLC (“Mountain Valley”)...more

FERC and Montana Supreme Court Issuances Bring Big Regulatory Shakeups to the PURPA Regulatory Landscape

On September 1, 2020, FERC issued an order overturning 40 years of Public Utility Regulatory Policies Act of 1978 (“PURPA”) precedent and revoking the qualifying facility (“QF”) status of Broadview Solar, LLC (“Broadview...more

11 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide