When a party fails to comply with a condition precedent, especially if such a provision includes a time limit for the fulfilment of the obligation, it will often advance various arguments to avoid the consequences of...more
6/13/2024
/ Commercial Contracts ,
Construction Contracts ,
Construction Litigation ,
Construction Project ,
Contract Disputes ,
Contract Interpretation ,
Contract Terms ,
Data Breach ,
Notice Requirements ,
Subcontractors ,
UK
In the case of Bellway Homes Limited v Surgo Construction [2024] EWHC 10 TCC, the court addressed whether it is possible to start a smash & grab adjudication but also a claim based on true value adjudication as a secondary...more