Entitlement Ruling Obtained on $5.7 Million Dredging Dispute

Cohen Seglias Pallas Greenhall & Furman PC
Contact

An entitlement ruling was secured for a dredging contractor in a $5.7 million claim against the U.S. Army Corps of Engineers. The Armed Services Board of Contract Appeals (ASBCA) ruled that the government withheld superior knowledge and issued defective specifications concerning a 2022 dredging project located in Newburyport Harbor, Massachusetts.

In this case, the government awarded a client a contract to dredge a harbor channel. Following contract award, the contractor attempted to self-perform dredging using a cutterhead dredge, but soon found that the channel sea conditions were more severe than stated in the solicitation. The contractor was unable to self-perform and was eventually forced to subcontract dredging to a larger, ocean-going dredge, at added cost.

It was subsequently discovered that an earlier government solicitation specifically warned bidders about the channel’s rough sea conditions and required the use of a dredge insured for use in ocean conditions. It was also discovered that the government had withheld reports and data demonstrating that the channel experienced large swells and had become more dangerous in recent years.

Based on the government’s failure to disclose these warnings and information, the contractor submitted a claim alleging that the government possessed superior knowledge and issued defective specifications. The government, however, denied the claim and argued that the contractor should have discovered the channel’s sea conditions from publicly available sources, among other arguments.

On appeal, the ASBCA rejected the government’s position. The ASBCA found that the warnings and information contained in the earlier solicitation and government reports constituted vital information that should have been disclosed to bidders. The ASBCA also found that the contractor had reasonably assessed the 2022 solicitation and available information, including because the government’s pre-award independent estimate had estimated channel conditions similar to those anticipated by the contractor. The contractor and the government will now seek to resolve the amount to be paid to the contractor on its $5.7 million claim.

A copy of the ruling may be found here

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations. Attorney Advertising.

© Cohen Seglias Pallas Greenhall & Furman PC

Written by:

Cohen Seglias Pallas Greenhall & Furman PC
Contact
more
less

PUBLISH YOUR CONTENT ON JD SUPRA NOW

  • Increased visibility
  • Actionable analytics
  • Ongoing guidance

Cohen Seglias Pallas Greenhall & Furman PC on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide