The Impact of Government Indecision on Government Contractors

Cohen Seglias Pallas Greenhall & Furman PC
Contact

Disputes frequently arise because the government refuses to agree that a contractor is entitled to additional money or time resulting from constructive changes, differing site conditions, government-caused delays, or countless other reasons. These disagreements typically are dealt with through the submission of Requests for Equitable Adjustment (REAs) or certified claims and are ultimately resolved through the disputes process. They focus on the rights of the parties under the specific terms of the contract. The problem, however, is that contractors also incur costs because of government indecisiveness that has not yet generated an REA or claim under a particular contract clause. This places the contractor in a state of limbo, not knowing whether there will be a significant impact to the project.

The failure to promptly review and determine the acceptability of a submittal, respond to a Request for Information (RFI), or to review a shop drawing can have a significant impact on the cost and time of performance. As esteemed Professor Ralph Nash once observed, “indecision by the government can be very costly” and the “ball is in the government’s court” when a contractor puts the government on notice of a problem, submits a document for approval, or requests additional information. Nash & Cibinic Report, February 1988, Vol. 2, No. 2. Particularly frustrating are those situations where the government is guilty of lethargy or fails to act because necessary funding is not yet available. This causes the contractor to finance project performance to an extent that it could not have reasonably anticipated at the time of bidding.

To increase the chance of getting paid in a timely manner, contractors should diligently document the time lost and cost incurred as the result of government indecision. The government’s contracting and field personnel must be provided with prompt notice of the impact of the government’s failure to act with specific reference to the possibility that a claim might result. Above all, government representatives must be reminded that contractors are not bankers and they are not in the business of providing financing for the additional costs that arise because of government inaction or indecision.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations. Attorney Advertising.

© Cohen Seglias Pallas Greenhall & Furman PC

Written by:

Cohen Seglias Pallas Greenhall & Furman PC
Contact
more
less

PUBLISH YOUR CONTENT ON JD SUPRA NOW

  • Increased visibility
  • Actionable analytics
  • Ongoing guidance

Cohen Seglias Pallas Greenhall & Furman PC on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide