Protest of: BrightPoint, LLC - B-423392, B-423392.2, B-423392.3 - BrightPoint raised numerous challenges to the Department of Agriculture’s evaluation and award of a task order for information technology services....more

Pillsbury - Bid Protest Debrief

Wright Brothers Protest Fails to Take Flight: GAO Grounds Untimely Protest

In Wright Brothers Aero, Inc., B-423326.2 (July 7, 2025),​ Wright Brothers Aero protested the Defense Logistics Agency’s (DLA) reaffirmation of a contract award for aircraft refueling services to Premier Jet Services, arguing...more

Fox Rothschild LLP

OCIs: Recent GAO Decision Provides Insight on How to Successfully Challenge an Agency’s Investigation of Organizational Conflicts...

Fox Rothschild LLP on

The Federal Acquisition Regulation (FAR) generally requires contracting officials to identify and evaluate organizational conflicts of Interest (OCIs) as early as possible in a procurement. The FAR also requires the procuring...more

Bass, Berry & Sims PLC

Compliance with Limitation on Subcontractor is Ostensible Subcontractor Safe Harbor

On June 2, the Small Business Administration’s (SBA) Office of Hearing and Appeals (OHA) denied a size appeal filed by Veteran Elevator Solutions, LLC (VES) challenging the size of Bass, Berry & Sims’ client GD Resources, LLC...more

Davis Wright Tremaine LLP

ASBCA Denies a Service Contractor's Appeal for Additional Labor Costs

The U.S. Armed Services Board of Contract Appeals' recent decision in HD Inc., ASBCA 63794, demonstrates the importance of following the terms of a solicitation when submitting a proposal on federal projects, particularly as...more

PilieroMazza PLLC

Weekly Update for Government Contractors and Commercial Businesses – June 2025 #4

PilieroMazza PLLC on

Can Contractors Recover Damages for Arbitrary CPAR Ratings? The ASBCA Weighs In - Every seasoned government contractor knows the weight a negative Contractor Performance Assessment Report (CPAR) can carry. A blemish in the...more

PilieroMazza PLLC

Can Contractors Recover Damages for Arbitrary CPAR Ratings? The ASBCA Weighs In

PilieroMazza PLLC on

Every seasoned government contractor knows the weight a negative Contractor Performance Assessment Report (CPAR) can carry. A blemish in the CPAR System (CPARS) can mean the difference between winning a new contract or losing...more

Fox Rothschild LLP

CDA Claim Management Primer: Suspension of Work (FAR 52.242-14)

Fox Rothschild LLP on

Federal construction contracts often involve unforeseen delays. The key question is who is responsible for the resulting costs. A new decision from the ASBCA provides a blueprint for how contractors can maximize recovery...more

Bradley Arant Boult Cummings LLP

Understanding the FAA’s ODRA Bid Protest Process: A Guide for Government Contractors

When it comes to federal procurements, the Federal Aviation Administration (FAA) operates a little differently than most other agencies. Unlike other federal agencies that follow the Federal Acquisition Regulation (FAR), the...more

Bradley Arant Boult Cummings LLP

Understanding Small Business Size and Status Protests and Appeals: A Guide for Government Contractors

In the highly competitive world of federal government contracting, a firm’s small business size or socioeconomic status can determine its eligibility for lucrative set-aside contracts. For competitors and interested parties,...more

Morrison & Foerster LLP - Government...

Bid Protest Spotlight: Size, Supply Schedules, SINs

This month’s Law360 Bid Protest Roundup focuses on two Government Accountability Office (“GAO”) decisions and one Office of Hearings and Appeals (“OHA”) decision. From General Services Administration (“GSA”) Schedule holders...more

Bradley Arant Boult Cummings LLP

Competitive Range Determination Violated the FAR, Court Finds

The U.S. Court of Federal Claims recently issued a significant opinion in Gemini Tech Servs., LLC v. United States, holding that the Army’s failure to follow required procedures under the Federal Acquisition Regulation (FAR)...more

PilieroMazza PLLC

6 Effective Tactics to Help Government Contractors Overcome Unfavorable CPARS Evaluations

PilieroMazza PLLC on

In federal contracting, your reputation is currency, and few tools can shape that reputation more than the Contractor Performance Assessment Reporting System (CPARS). CPARS evaluations don’t just sit in a file, they’re pulled...more

Davis Wright Tremaine LLP

Not To Be Heard: CBCA Dismisses a Contractor's Appeal of a Termination for Convenience for Lack of Jurisdiction

At a time when government agencies are terminating contracts for convenience at an increasingly high rate, a recent decision by the U.S. Civilian Board of Contract Appeals in Blankson v. Agency for International Development,...more

Blank Rome LLP

A Roadmap for Terminations for Convenience in the DOGE-Era

Blank Rome LLP on

The Department of Government Efficiency’s (“DOGE”) scrutiny of federal contracts has resulted in a spike in notices of termination for convenience. Given DOGE’s broad mandate to reduce federal spending, we expect a sustained...more

Seyfarth Shaw LLP

Six Essential Tips for Navigating the Contract Claims Process in Government Contracting

Seyfarth Shaw LLP on

In celebration of the release of the 6th Edition of the Government Contracts Compliance Handbook, we are sharing six essential tips for successfully navigating the contract claims process under federal procurement...more

Ogletree, Deakins, Nash, Smoak & Stewart,...

President Trump Ends $15-Per-Hour Contractor Minimum Wage Rate After Filing a Brief Defending Power to Set the Minimum Wage

On March 14, 2025, President Donald Trump issued Executive Order (EO) 14236—“Additional Rescissions of Harmful Executive Orders and Actions”—revoking eighteen executive orders and actions issued by former president Joe Biden....more

Bass, Berry & Sims PLC

SBA’s OHA Finds Initial Offer To Be Of Consequence, Not Final Proposal Revision, for the “180-Day Rule”

Bass, Berry & Sims PLC on

On February 19, the Office of Hearings and Appeals (OHA) denied an appeal from an unsuccessful bidder who argued the awardee was large due to an acquisition that occurred while the award was pending. OHA found that Small...more

Bradley Arant Boult Cummings LLP

What to Do If the Government Doesn’t Pay You as a Federal Contractor

Winning a federal contract can be a significant opportunity, but what happens if the government doesn’t pay you on time — or at all? While the federal government is typically a reliable payer, delays or disputes can arise,...more

Morrison & Foerster LLP - Government...

Bid Protest Spotlight: Registration, Substantiation, Experience

To kick off the new year, this bid protest spotlight highlights two U.S. Government Accountability Office decisions involving System for Award Management (SAM) registration requirements when submitting an “offer” and an...more

Jenner & Block

Client Alert: The Price of Silence: GAO Dismisses Protest Because the Protester’s Key Personnel Were Unavailable

Jenner & Block on

On December 30, 2024, the Government Accountability Office (GAO) dismissed a protest by Orion Government Services, Inc. (Orion) after determining that Orion lacked standing to protest because one of its proposed key personnel...more

Bradley Arant Boult Cummings LLP

The 5 Most Important Bid Protest Decisions Of 2024

In 2024, the U.S. Court of Appeals for the Federal Circuit, the U.S. Court of Federal Claims and the U.S. Government Accountability Office issued five noteworthy bid protest decisions: - Percipient.ai Inc. v. U.S. - Oak...more

Jenner & Block

Government Contracts Legal Round-Up – 2024 Issue 6

Jenner & Block on

Claims Updates - Avue Technologies Corp. v. Department of Health & Human Services, No. 2022-1784 Fed. Cir. (March 6, 2024) The Federal Circuit issued its much-anticipated decision in a case that presented the question...more

Davis Wright Tremaine LLP

What Constitutes a Reasonable Period of Time Under the Suspension-of-Work Clause?

In Granite Construction Company, ASBCA No. 62281 (November 1, 2023), the Armed Services Board of Contract Appeals ("Board") addressed the issue of what constitutes a reasonable period of time to suspend work under the...more

Davis Wright Tremaine LLP

Federal Circuit Clarifies the De Novo Review Standard for a Termination for Default

Department of Transportation v. Eagle Peak Rock & Paving, Inc., concerns a $35 million contract that the U.S. Department of Transportation Highway Administration ("FHWA") awarded to Eagle Peak Rock & Paving, Inc. ("Eagle...more

49 Results
 / 
View per page
Page: of 2

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide