News & Analysis as of

Construction Disputes Federal Contractors

Fox Rothschild LLP

CDA Claim Management Primer: Suspension of Work (FAR 52.242-14)

Fox Rothschild LLP on

Federal construction contracts often involve unforeseen delays. The key question is who is responsible for the resulting costs. A new decision from the ASBCA provides a blueprint for how contractors can maximize recovery...more

Blank Rome LLP

The Bottom Line: Cost and Pricing Updates | Act of God or Compensable Delay?

Blank Rome LLP on

Welcome to The Bottom Line: Cost and Pricing Updates, a new series covering what contractors should know about recent cost and pricing disputes—without the long read!...more

Seyfarth Shaw LLP

Federal Circuit Nullifies Sum Certain Contract Disputes Act Jurisdictional Defense

Seyfarth Shaw LLP on

In ECC Int’l Constructors, LLC v. Sec’y of Army, No. 2021-2323, 2023 WL 5355302 (Fed. Cir. Aug. 22, 2023), the U.S. Court of Appeals for the Federal Circuit considered whether the Federal Acquisition Regulation (“FAR”)...more

Davis Wright Tremaine LLP

If Ya Snooze, Ya Lose ($12 Million): Strict Application of Dispute Procedures Bar Contractor Claim Against State Agency

The key takeaway from Graham Contracting, Ltd v. City of Federal Way in Washington appeals court - A recent unpublished decision issued by the Court of Appeals of Washington, Graham Contracting, Ltd v. City of Federal...more

Robinson+Cole Construction Law Zone

Connecticut Court Clarifies a Limit on Payment Bond Claims for Public Projects

In All Seasons Landscaping, Inc. v. Travelers Casualty & Surety Co., No. DBD-CV21-6039074-S, 2022 WL 1135703 (Conn. Super. Ct. April 4, 2022) the plaintiff, a subcontractor on a state project, commenced a lawsuit against the...more

Spilman Thomas & Battle, PLLC

The Site Report - Construction Law Insights, Issue 12, December 2022

Welcome to the 12th and final issue of the year for The Site Report. Top Three Construction Disputes and How to Avoid Them - Construction professionals sometimes feel as if it is déjà vu when it comes to disputes—and they...more

Bradley Arant Boult Cummings LLP

Timing Is Everything: Miller Act Notice Defect Saves Surety

The Miller Act protects subcontractors from nonpayment on federal projects by requiring prime contractors to issue payment bonds. To obtain relief under the Miller Act, a subcontractor must (1) give the prime contractor...more

Buchalter

Email Sent After Final Payment Held Insufficient to Preserve Timeliness of Claim Against Government

Buchalter on

They say that hindsight is 20/20. Who is they, anyway? The old proverb means that it is easy to understand something after it has already happened. In the world of construction contracts, preservation of claims made in...more

Buchalter

Contractor Learns You Need an Expert to Join “Battle of the Experts”

Buchalter on

It kind of goes without saying, but you should probably bring your expert to a dispute if there is going to be a battle of the experts. One contractor recently learned this lesson to the tune of $65,000....more

Troutman Pepper Locke

Federal Court In Mississippi Holds That Although Projects Were Constructed With Federal Funds, They Were Not “A Public Work Of The...

Troutman Pepper Locke on

United States ex rel. Metro Mech., Inc. v. Triangle Constr. Co., 2018 U.S. Dist. LEXIS 1487 (S.D. Miss. Jan. 4, 2018) - Triangle Construction Company, Inc. (“Triangle”) contracted with Mississippi Portfolio Partners III,...more

Bradley Arant Boult Cummings LLP

The Consequences of Failing to Exhaust Administrative Remedies Prior To Filing Suit - Construction and Procurement Law News, Q3...

The Fourth Circuit Court of Appeals, the federal appeals court covering Maryland, Virginia, West Virginia, North Carolina, and South Carolina, affirmed the trial court’s decision to dismiss a contractor’s breach of contract...more

Bradley Arant Boult Cummings LLP

My Roof, My Rules: Arbitrators May Determine Their Own Jurisdiction When the Parties Delegate that Authority

An issue that repeatedly comes up in construction disputes is the scope of an arbitration agreement. Courts generally interpret agreements to arbitrate broadly, and, where the arbitrability of a specific claim has been at...more

Troutman Pepper Locke

Federal Court in Alabama Rules that 1999 Amendment to the Miller Act Does Not Preclude Arbitration of Underlying Claims

Troutman Pepper Locke on

United States v. Int’l Fid. Ins. Co., No. 16-0472-WS-C, 2017 U.S. Dist. LEXIS 16791 (S.D. Ala. Feb. 7, 2017) - This action arose out of a payment dispute between Bay South Limited, Inc. (“Bay South”) and Stephens...more

Cozen O'Connor

Infrastructure Alert - February 11, 2014

Cozen O'Connor on

The Panama Canal Authority and the GPUC, the construction consortium working on its expansion, have been deadlocked over whether the Canal will pay for $1.6 billion in cost overruns. Construction halted on February 5 due to...more

14 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide