News & Analysis as of

Court of Federal Claims Bid Solicitation

Cozen O'Connor

U.S. Court of Federal Claims Finds Project Labor Agreements Violate the Competition in Contracts Act

Cozen O'Connor on

On January 21, 2025, Judge Ryan T. Holte of the U.S. Court of Federal Claims issued a decision finding now former-President Biden’s February 4, 2022, Executive Order 14063 (EO) and the resulting Federal Acquisition...more

Mayer Brown

Ruling on an Issue of First Impression, US COFC Finds Protest Jurisdiction Over Challenge to a Follow-On Production Other...

Mayer Brown on

On July 16, 2024, the Court of Federal Claims (“COFC” or “Court”) published an opinion, Independent Rough Terrain Center, LLC v. United States, exercising jurisdiction to consider a bid protest involving Other Transaction...more

Cozen O'Connor

Federal Circuit Increases Jurisdictional Scope for Bid Protests in Percipient.ai, Inc. v. United States

Cozen O'Connor on

On June 7, 2024, the U.S. Court of Appeals for the Federal Circuit broadened the Court of Federal Claims’ ability to oversee bid protests in Percipient.ai, Inc. v. United States. This case arose out of a bid protest to an...more

Sheppard Mullin Richter & Hampton LLP

What Makes a Successful Protest at the Court of Federal Claims

In a previous article, we analyzed what made protests successful at the Government Accountability Office (“GAO”) in Fiscal Year 2023 (“FY23”). Now, we want to share some insights we gained while conducting the same analysis...more

Jenner & Block

Government Contracts Legal Round-Up – 2024 Issue 4

Jenner & Block on

Court of Federal Claims Bid Protest Update - Netcentrics Corporation v. United States and Rockwell Collins, Inc. v. United States - Two recent Court of Federal Claims decisions reaffirm that the Court will meaningfully...more

Hogan Lovells

Highlights with Hogan Lovells: Bid Protest Digest | Volume V

Hogan Lovells on

This issue of bid protest highlights includes key takeaways from the U.S. Government Accountability Office’s (GAO) Bid Protest Annual Report to Congress for Fiscal Year 2023, as well as bid protest decisions from the U.S....more

Sheppard Mullin Richter & Hampton LLP

Bid Protest Hub – November 2023

Since the beginning of Fiscal Year 2024, the Government Accountability Office has published 35 decisions, but only two of which resulted in decisions sustaining the challenge. As contracting activities are busy awarding new...more

Morrison & Foerster LLP - Government...

June 2023 Bid Protest Roundup: Errors, Experience, Corrective Action

This month’s bid protest roundup focuses on two decisions from the U.S. Court of Federal Claims (“Court”) and one decision from the U.S. Government Accountability Office (“GAO”). These decisions involve (1) the Court’s...more

Morrison & Foerster LLP - Government...

May 2022 Bid Protest Roundup: Errors, Subcontractors, Bundling

This month's bid protest spotlight focuses on one recent U.S. Court of Federal Claims decision and two U.S. Government Accountability Office decisions. While all three protests were unsuccessful, each serves as a different...more

Morrison & Foerster LLP - Federal Circuitry

Last Week in the Federal Circuit (August 10-14): Clear Skies for Boeing After No-Waiver Ruling

Last week was apparently CFC week at the Federal Circuit, with several precedential decisions in government contracts and Tucker Act cases. Below we give our usual week’s statistics and case of the week—our highly subjective...more

Carlton Fields

Contra Dicta-ry: Your Agency Challenge May Be Waived, Even If Cases Say You “Likely” Preserved It

Carlton Fields on

The Court of Federal Claims’ decision in Harmonia Holdings Group, LLC v. United States serves as a stark reminder to be wary when relying on dicta supporting your position. ...more

Bass, Berry & Sims PLC

Tis the Season (for Protests)!

Bass, Berry & Sims PLC on

The government fiscal year runs from October 1 to September 30, and at the end of each fiscal year federal agencies rush to award contracts and commit funding before that funding expires. As a result, our Government Contracts...more

Williams Mullen

Award Protests: Choosing the Forum

Williams Mullen on

A disappointed bidder’s protest strategy includes deciding whether to initiate the protest with the procuring agency, the Government Accountability Office or the U. S. Court of Federal Claims....more

13 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide