Building Design Disputes – New Analysis of Direct v. Consequential Damages in Florida

Are design professionals involved in your Florida project? If so, then you need to be aware of this newly decided case. The U.S. District Court for the Middle District of Florida, in Orlando, issued an Order on July 11,...more

Bradley Arant Boult Cummings LLP

Court Rejects Subcontractor’s Safety Excuse for Jumping Ship

A federal judge in Oklahoma last week ruled against an electrical subcontractor who quit work before finishing because it was allegedly unsafe to continue. The court found that the subcontractor was simply losing money, and...more

Bradley Arant Boult Cummings LLP

Second Circuit: No-Damages-For-Delay Clause Bars Claim

The Second Circuit Court of Appeals recently applied a no-damages-for-delay provision to affirm the dismissal of a demolition contractor’s breach of contract claims. The project involved reconstructing and raising the Bayonne...more

Bradley Arant Boult Cummings LLP

Court Affirms Dismissal of Subcontractor’s Wrongful Termination Counterclaim and Clarifies Scope of Upcoming Trial on Damages

Back in April we examined the court’s decision in Boldt v. Black & Veatch, which dismissed a subcontractor’s counterclaim for wrongful termination on a 60-turbine wind farm project. As you may recall, the subcontractor hired...more

Bradley Arant Boult Cummings LLP

Damages in Construction Claims: Are “Actual Costs” Actually Required?

The golden standard for the measure of damages in a construction case alleging defective or incomplete work are the actual costs of completion or repair. That is to say, if there is a breach (or multiple breaches) of quality...more

Bradley Arant Boult Cummings LLP

Risk Assessment — Construction Claims: How to Calculate the Recoverable Costs and Damages

When negotiating a complex change order or preparing to litigate a claim, calculating actual recoverable costs incurred can be a difficult exercise. You will want to first review your contract to determine what kinds of costs...more

Bradley Arant Boult Cummings LLP

Casting the First Stone: Contractors Considering Default Termination Should Examine Which Party Committed First Material Breach -...

During a construction project, circumstances may arise that lead a general contractor to consider termination of a subcontractor’s right to proceed under the subcontract. The Randy Kinder Excavating v. J.A. Manning...more

Troutman Pepper Locke

Contractor Has No Duty To Indemnify Gas Company For Settlement Paid To Injured Employee Under Florida’s Underground Facility And...

Troutman Pepper Locke on

Peoples Gas Sys. v. Posen Constr., Inc., 2018 U.S. Dist. LEXIS 106427 (M.D. Fla. June 26, 2018) - In 2009 Posen Construction, Inc. (“Posen”), a road construction contractor, entered into a general contractor agreement with...more

Bradley Arant Boult Cummings LLP

Alternative Measures of Damages in Real Property Disputes in Tennessee

When it comes to actions arising out of damage to property by a contractor, especially in the residential real property context, Tennessee courts typically balance the cost to repair versus the diminution in value of the...more

Kilpatrick

Choosing a Damages Methodology for Certain Construction Claims

Kilpatrick on

In any construction dispute resolution process, not only does a claimant have to prove liability of the other party, but the claimant must also prove damages to prevail on its claim. The proof of damages element to...more

Haight Brown & Bonesteel LLP

Appeals Court Finds Manuscript Additional Insured Endorsements Ambiguous Regarding Completed Operations Coverage for Additional...

In Pulte Home Corp. v. American Safety Indemnity Co. (No. D070478; filed 8/30/17), a California appeals court found that manuscript additional insured endorsements on construction subcontractors’ policies were ambiguous...more

Troutman Pepper Locke

Alert to Contractors – California Court of Appeals (2d App. Dist.) Rules Subcontractor Price in Proposal Containing Material...

Troutman Pepper Locke on

Flintco Pacific, Inc. v. TEC Management Consultants, Inc., 2016 Cal. App. LEXIS 594 (Cal. App. 2d Dist. June 21, 2016) - There was an important California decision published on July 19, 2016 (decided June 21, 2016)...more

Carlton Fields

Construction Case Law Update - July 2015

Carlton Fields on

Involuntary Dismissal of Counterclaims – In a suit between a developer and general contractor, the trial court erred in dismissing the general contractor’s counterclaims, without a motion by the developer, before the...more

13 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide