Court Affirms $1 Nominal Damage Award in Wind Farm Construction Dispute

Court Affirms $1 Nominal Damage Award in Wind Farm Construction Dispute The general contractor on the 60-turbine wind farm project in Good Hope, Illinois, is entitled to collect a whopping $1 on its cost-to-complete claim...more

Bradley Arant Boult Cummings LLP

Yes, Damages for Delay: Court Permits Delay Damage Claim to Proceed

A federal court in upstate New York is permitting a subcontractor’s delay claim to proceed notwithstanding a “no damages for delay” provision in the subcontract. The case, The Pike Company, Inc. v. Tri-Krete, Ltd., involves...more

Rumberger | Kirk

Adapting to Change: New Rules of Civil Procedure Require New Considerations for Construction Attorneys

Rumberger | Kirk on

On Jan. 1, 2025, the Florida Rules of Civil Procedure changed dramatically. The new rules and amendments are designed to enhance efficiency and impact the setting of cases for trial, case management, discovery practice,...more

Bradley Arant Boult Cummings LLP

Put Up or Shut Up: Court Grants Summary Judgment for Steel Sub in Price Escalation Clause Dispute

An Illinois federal court ruled in favor of steel subcontractor Nucor in its contract dispute with Direct Steel. The project involved the construction of pre-engineering metal buildings for the Army Corps of Engineers. The...more

Bradley Arant Boult Cummings LLP

Failure by Injured Party to Take Reasonable Action May Limit Recovery - Construction and Procurement Law News, Q2 2018

There are instances where a party’s breach of the construction contract is undisputed. However, the amount of recoverable damages often hinges on the injured party’s own conduct both during and following that breach. The...more

Carlton Fields

Appeal it All! Guarding Against Multiple, Independent Grounds

Carlton Fields on

You’ve identified a killer issue for appeal, no doubt a winner. Congratulations! You still lose. How can that be? In Novum Structures, LLC v. Choate Construction Company, Inc., 698 Fed. Appx. 608 (11th Cir. 2017), the...more

Carlton Fields

Construction Case Law Update - July 2015

Carlton Fields on

Involuntary Dismissal of Counterclaims – In a suit between a developer and general contractor, the trial court erred in dismissing the general contractor’s counterclaims, without a motion by the developer, before the...more

7 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide