To assert a claim for monetary relief, the claimant must seek a "sum certain." A monetary claim that does not state a sum certain may be denied by the Contracting Officer and denied by the Board of Contract Appeals for...more
Federal contractors understandably associate litigation at the Court of Federal Claims (COFC) with recovering monetary damages. Appealing denied claims to the COFC (along with the Boards of Contract Appeals) is the exclusive...more