Electricity Regulatory Requirements Settlement

Baker Botts L.L.P.

FERC Approves First Enforcement Settlement Involving Power Plant Operations by Bitcoin Mining Company.

Baker Botts L.L.P. on

Bitcoin mining company pays $1.42 million for violating PJM’s tariff in relation to its power plant operations. On January 30, 2025, the Federal Energy Regulatory Commission (“FERC”) approved a settlement agreement...more

Troutman Pepper Locke

FERC Approves Contested Settlement Agreement and Rate Schedule for Provision of Reliability Must-Run Service

Troutman Pepper Locke on

On January 16, 2025, FERC approved a contested settlement agreement and rate schedule governing the provision of reliability must-run (“RMR”) service from the Indian River Unit 4 generating facility (“Unit 4”) in PJM...more

2 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide