Bid Protest Minute: Insufficient Funds are Grounds to Cancel

Bass, Berry & Sims PLC on

On April 29, the Government Accountability Office (GAO) denied Davenergy-VCI JV, LLC’s protest of a solicitation’s cancellation, holding that the lack of available funding is sufficient grounds to cancel. In denying the...more

Pillsbury - Bid Protest Debrief

No Funding, No Award: GAO Upholds Corps’ Late-Stage Solicitation Cancellation

In Davenergy-VCI JV, LLC, B-423332, April 29, 2025​, Davenergy-VCI protested the cancellation by the Army Corps of Engineers (Corps) of a solicitation for architectural engineering construction management services for medical...more

Bradley Arant Boult Cummings LLP

GAO Sustains Protest Challenging Decision to Convert Competitive Bid Solicitation to Negotiated Procurement

In January 2023, the U.S. Army Corps of Engineers (USACE) issued an invitation for bids (IFB) for a dune and berm replenishment and renovation project along the New Jersey coast. The USACE received two sealed bids for the...more

Fox Rothschild LLP

COFC Says GAO has been wrong on Photocopied Bid Bond Signatures for Decades

Fox Rothschild LLP on

Late last year, the Court of Federal Claims (“COFC”) contradicted long-standing Government Accountability Office (“GAO”) precedent on the acceptability of photocopied signatures on bid bonds finding that the Government’s...more

Morrison & Foerster LLP - Government...

December 2023 Bid Protest Roundup: Supplementation, Conversion, Rejection

This month’s Bid Protest Roundup include decisions regarding supplementation of the record and whether an agency may convert a sealed bid opportunity into a negotiated procurement due to lack of funds, as well as a case in...more

Perkins Coie

Federal Circuit Holds “Sum Certain” Requirement in Government Contracts Cases Is Nonjurisdictional

Perkins Coie on

Clarifying a significant issue in government contracts litigation against the government, the U.S. Court of Appeals for the Federal Circuit has held that the so-called “sum certain” requirement for Contract Disputes Act (CDA)...more

Bass, Berry & Sims PLC

Bid Protest Win for AM General on Multi-Billion Dollar Contract

Bass, Berry & Sims PLC on

We represented AM General (AMG), an automotive manufacturer that builds military vehicles for government customers, including the Humvee, in a successful bid protest involving a $9.7 billion contract for the U.S. Army to...more

Morrison & Foerster LLP - Government...

March 2023 Bid Protest Roundup: Review, Self-Certification

This month's bid protest spotlight considers two recent protests. J.E. McAmis Inc. v. U.S. is an important decision by the U.S. Court of Federal Claims concerning the court's lack of authority to review the U.S. Small...more

PilieroMazza PLLC

Weekly Update for Government Contractors and Commercial Businesses – December 2022

PilieroMazza PLLC on

GOVERNMENT CONTRACTS - 2022 GAO Bid Protest Annual Report: Key Takeaways for Government Contractors - The Government Accountability Office (GAO) recently released its 2022 Bid Protest Annual Report (Report), which...more

Jenner & Block

Government Contracts Legal Round-Up | 2022 Issue 9

Jenner & Block on

Welcome to Jenner & Block’s Government Contracts Legal Round‑Up, a biweekly update on important government contracts developments. This update offers brief summaries of key developments for government contracts legal,...more

Pillsbury Winthrop Shaw Pittman LLP

Federal Circuit Clarifies Bid Protest Stay Timeliness Rules

The U.S. Court of Appeals for the Federal Circuit confirms that a protester seeking to avail itself of the statutory “automatic stay” of performance in connection with a GAO bid protest must file that protest within five days...more

Pillsbury Winthrop Shaw Pittman LLP

Corrective Action Catch 22: Court of Federal Claims Holds Agency Action Must Be Rational Even If GAO Protest Decision Was Not.

The United States Court of Federal Claims’ July 15, 2014 decision in RUSH Construction, Inc. v. United States, reflects the unusual circumstance in which the court effectively sat in appellate review of an earlier bid protest...more

12 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide