DC Circuit Embraces Seven County in FERC Pipeline Review Proceeding

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot...more

Troutman Pepper Locke

D.C. Circuit Denies Healthy Gulf’s and Sierra Club’s Petition for Review of FERC Order Authorizing Construction and Operation of...

Troutman Pepper Locke on

On March 28, 2025, the D.C. Circuit denied a joint petition for review brought by Healthy Gulf and Sierra Club (together, “Petitioners”) challenging FERC’s grant of a certificate of public convenience and necessity (CPCN) to...more

Morgan Lewis

DC Circuit Rejects FERC’s Use of Tolling Orders; FERC Issues Statement Asking Congress to Act

Morgan Lewis on

A decision by the US Court of Appeals for the DC Circuit on June 30 rejected the near routine use by the Federal Energy Regulatory Commission of tolling orders to prevent rehearing requests from being denied by operation of...more

Bricker Graydon LLP

D.C. Circuit bars long-standing FERC rehearing tolling practice

Bricker Graydon LLP on

On June 30, 2020, the U.S. Court of Appeals for the D.C. Circuit, sitting en banc, denounced the practice of the secretary of the Federal Energy Regulatory Commission (FERC) in issuing tolling orders, which provide FERC with...more

Davis Wright Tremaine LLP

D.C. Circuit Ends FERC Practice of Delaying Judicial Review Through Tolling Orders

The U.S. Court of Appeals for the D.C. Circuit, sitting en banc, has ruled that the Federal Energy Regulatory Commission (FERC) cannot delay the time for a judicial appeal by issuing a tolling order. FERC's long-standing...more

Pierce Atwood LLP

DC Circuit Rejects FERC’s Tolling Authority in Pipeline Certificate Proceedings

Pierce Atwood LLP on

The Federal Energy Regulatory Commission (“FERC”) can no longer delay judicial review of its orders under the Natural Gas Act by issuing a tolling order that takes no action on a rehearing request other than granting itself...more

6 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide