News & Analysis as of

Liquidated Damages Breach of Contract Construction Industry

Gray Reed

Disrupted Operations – Owners Beware! – Part 2 (DAMAGES)

Gray Reed on

Liquidated damages are intended to provide predictability to the owner and contractor as to the financial consequence of not completing a project in a timely manner. Since liquidated damages are intended to compensate the...more

Bowditch & Dewey

Liquidated Damages v. Actual Damages – Which Is the Better Choice?

Bowditch & Dewey on

Liquidated damages provisions are common to all types of agreements, from leases to construction contracts. While liquidated damages provisions may appear “boilerplate” and full of legalese, they profoundly impact how much a...more

Stoel Rives -  Ahead of Schedule

The Role of Liquidated Damages Provisions in Construction Contracts

Considering all that can go wrong on a construction site, it can seem like a miracle that anything is ever built. Construction projects can be massive undertakings, often with millions of dollars at stake, requiring the...more

Bradley Arant Boult Cummings LLP

Liquidated Damages Disproportionate to Actual Damages Deemed Unenforceable

Construction contacts often include provisions that provide for pre-determined or “liquidated” damages in the event of a breach. Such provisions can provide certainty to the parties as to the consequences of a breach and can...more

BCLP

Can liquidated damages clauses set general cap?

BCLP on

A pair of cases in the past two years have come to opposite conclusions about whether general damages can be capped by contract provisions for liquidated damages. Liquidated damages clauses are a common feature of...more

Porter Hedges LLP

Tips on Drafting Enforceable and Effective Liquidated Damages Provisions Under Texas Law

Porter Hedges LLP on

Liquidated damages provisions are commonplace in construction contracts. One would think that given the strong Texas public policy favoring freedom of contract, bargained for liquidated damages would be easily enforceable in...more

White & Case LLP

Managing construction risks in Asia-Pacific: Vietnam

White & Case LLP on

Changes in the construction law and favorable government policy continue to spur Vietnam's construction industry. Vietnam is the third-largest country in Southeast Asia. Due to favorable government policy and an abundance...more

White & Case LLP

Managing construction risks in Asia-Pacific: Singapore

White & Case LLP on

With a significant and coherent body of case law on construction disputes, Singapore is a hub for resolving many construction disputes across the Asia-Pacific region. Singapore is a vibrant country in Southeast Asia. With...more

White & Case LLP

Managing construction risks in Asia-Pacific: Philippines

White & Case LLP on

The Philippines construction industry is expected to grow with the introduction of the "Build, Build, Build" initiative and the amendment of a number of laws that would loosen restrictions on foreign investment. The...more

White & Case LLP

Managing construction risks in Asia-Pacific: Indonesia

White & Case LLP on

The construction industry in Indonesia has long been considered the backbone of the country's economic and social development, and regulations are being continuously amended to ease complexity and expedite processes for...more

BCLP

Triple Point v PTT: UK Supreme Court also interprets a contractual cap on liability

BCLP on

The UK Supreme Court recently handed down a highly anticipated judgment on the interpretation of clauses which pertain to liquidated damages and limitations on a contractor’s liability for damages. Most notably, the Supreme...more

Ward and Smith, P.A.

Issues Impacting Enforceability of Liquidated Damages in Construction Contracts

Ward and Smith, P.A. on

Liquidated damages are a sum specified in a contract as the measure of recovery in the event of a breach of the contract. Liquidated damages provisions are common in construction contracts to guard against damages that the...more

Cohen Seglias Pallas Greenhall & Furman PC

[Webinar] Stipulated Sum and Liquidated Damages in Infrastructure Projects: What Are They, Are They Enforceable, and How Do You...

Most parties on a construction project know that a liquidated damage may be assessed for each day of the delay past a contract completion date. However, in infrastructure and highway contracts, there are many different events...more

Bennett Jones LLP

Supreme Court May Consider Enforceability of Liquidated Damages

Bennett Jones LLP on

On July 11, 2019, the Supreme Court of Canada (the SCC) granted leave to appeal from the Alberta Court of Appeal's decision in Capital Steel Inc v Chandos Construction Ltd, 2019 ABCA 32 [Chandos]. In a previous blog post, we...more

Troutman Pepper Locke

GAR Know-How Construction Arbitration - United States

Troutman Pepper Locke on

Legal System - 1. Is your jurisdiction primarily a common law, civil law, customary law or theocratic law jurisdiction? Are the laws substantially derived from the laws of another jurisdiction and, if so, which? What...more

Faegre Drinker Biddle & Reath LLP

Liquidated Damage Provisions – A Good Idea or an Unenforceable Penalty?

Construction contracts often contain a provision for a stipulated or “liquidated” damage amount in the event of specified contract breaches. These provisions can be an effective tool to recover losses that otherwise may go...more

Troutman Pepper Locke

Fourth Circuit Affirms Dismissal of Contractor’s Complaint, Declining to Create ‘Ultra Vires’ or ‘Bias’ Exceptions to the...

Troutman Pepper Locke on

Balfour Beatty Infrastructure, Inc. v. Mayor and City Council of Baltimore, 2017 U.S. App. Lexis 7252 (4th Cir., April 25, 2017) - The United States Court of Appeals for the Fourth Circuit recently addressed whether the...more

Snell & Wilmer

Under Construction - June 2017

Snell & Wilmer on

Welcome to the summer 2017 edition of our Under Construction newsletter. In this issue, to accompany the summer heat, we highlight several hot topic items affecting the construction industry, such as the recent revisions to...more

Troutman Pepper Locke

Ohio Supreme Court Holds Reasonableness of Liquidated Damage Provision to Be Determined Based Upon the Parties’ Knowledge at Time...

Troutman Pepper Locke on

Boone Coleman Constr., Inc. v. Vill. of Piketon, 2016-Ohio-628, 2016 Ohio LEXIS 441 (Ohio Feb. 24, 2016) - A general contractor entered into a construction contract with a public agency for a road construction project...more

19 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide