News & Analysis as of

Liquidated Damages Construction Disputes

Freiberger Haber LLP

Consequential Damages: Are They Foreseeable?

Freiberger Haber LLP on

In BLDG 44 Developers LLC v. Pace Companies N.Y., LLC, 2025 N.Y. Slip Op 32881(U) (Sup. Ct., N.Y. County July 25, 2025) (here), BLDG 44 Developers LLC sued Pace Companies New York, LLC for breach of contract, seeking...more

A&O Shearman

Watts at stake when there's a delay?

A&O Shearman on

The High Court has provided guidance on a contractor’s general right to suspend works, the enforceability of liquidated damages upon termination, and the recoverability of financing costs as part of loss of revenue....more

Robinson+Cole Construction Law Zone

A Liquidated Damages Provision Might Not Liquidate All Potential Damages

The purpose of a liquidated damages provision in a construction contract is to establish in advance a fair amount of compensation to the injured party for a breach of contract to avoid spending time and money fighting over...more

White & Case LLP

Managing construction risks in Asia-Pacific: Singapore

White & Case LLP on

With a significant and coherent body of case law on construction disputes, Singapore is a hub for resolving many construction disputes across the Asia-Pacific region. Singapore is a vibrant country in Southeast Asia. With...more

BCLP

Third time lucky: Supreme Court allows recovery of liquidated damages in Triple Point v PTT

BCLP on

Those you of you with an interest in construction law will no doubt have heard of the case of Triple Point v PTT, which concerned whether liquidated damages (LDs) are payable in the event of termination. The first...more

Cohen Seglias Pallas Greenhall & Furman PC

[Webinar] Stipulated Sum and Liquidated Damages in Infrastructure Projects: What Are They, Are They Enforceable, and How Do You...

Most parties on a construction project know that a liquidated damage may be assessed for each day of the delay past a contract completion date. However, in infrastructure and highway contracts, there are many different events...more

Troutman Pepper Locke

Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from...

Troutman Pepper Locke on

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would...more

Buchalter

When Does A Claim for Damages Not Require Notice? When It Is One For Liquidated Damages.

Buchalter on

I just blogged about asking for what you want and the importance of complying with notice provisions in pursuing a construction claim.  A court in Oklahoma just reminded me that not all claims require notice.  Here’s what I...more

BCLP

Willow v MTD: a successful Part 8 challenge after Hutton v Wilson

BCLP on

Following Hutton v Wilson, Part 8 challenges to adjudication have become less common. However, in Willow v MTD, the TCC has made a declaration setting aside part of an adjudicator’s decision where the adjudicator erred in his...more

Akin Gump Strauss Hauer & Feld LLP

The Court of Appeal in England & Wales Curtails Use of Liquidated Damages for Delay

In international construction arbitration, the use of liquidated damages to address the consequences of failure by a contractor to finish the works by the date set for completion is widespread. Typically, the contractor...more

White & Case LLP

Liquidated Damages for Post-Termination Delay?

White & Case LLP on

The High Court of England & Wales considered, in respect of the delayed completion of a solar project, the appropriate end date for liquidated damages under a terminated construction contract....more

Akin Gump Strauss Hauer & Feld LLP

Concurrent Delay – Is the English Court of Appeal's Clarification Conclusive?

• The Court of Appeal has held that a clause denying an extension of time to a Contractor if there is concurrent delay is enforceable and is not contrary to the so-called “prevention principle.” • The Court of Appeal...more

Troutman Pepper Locke

Under Louisiana Payment Act, Once Contractor Meets Contractual Requirements for Final Payment, Public Entity Has a Duty to Issue...

Troutman Pepper Locke on

Woodrow Wilson Constr. LLC v. Orleans Par. Sch. Bd., 2018 La. App. LEXIS 762 (April 18, 2018) - The Orleans Parish School Board (“OPSB”) awarded a prime contract to Woodrow Wilson Construction (“WWC”) for the construction...more

Troutman Pepper Locke

Ohio Supreme Court Holds Reasonableness of Liquidated Damage Provision to Be Determined Based Upon the Parties’ Knowledge at Time...

Troutman Pepper Locke on

Boone Coleman Constr., Inc. v. Vill. of Piketon, 2016-Ohio-628, 2016 Ohio LEXIS 441 (Ohio Feb. 24, 2016) - A general contractor entered into a construction contract with a public agency for a road construction project...more

14 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide