On March 28, 2025, the D.C. Circuit denied a joint petition for review brought by Healthy Gulf and Sierra Club (together, “Petitioners”) challenging FERC’s grant of a certificate of public convenience and necessity (CPCN) to...more
Since our last article discussing the way in which the Federal Energy Regulatory Commission ("FERC" or "the Commission") considers greenhouse gas (GHG) emissions and climate impacts in the pipeline certification process, the...more
In a recent opinion, the D.C. Circuit suggested the Federal Energy Regulatory Commission (FERC) must attempt to obtain information necessary to evaluate the environmental effects of a proposed interstate pipeline project due...more
Among other responsibilities, the Federal Energy Regulatory Commission ("FERC" or "the Commission") approves and issues construction certificates for interstate gas pipelines and related infrastructure under section 7 of the...more
On August 22, the US Court of Appeals for the District of Columbia Circuit, in a 2-1 decision, vacated and remanded orders of the Federal Energy Regulatory Commission (FERC) authorizing the construction and operation of three...more