Unpacking FERC's Transmission Planning and Permitting Final Rules
On May 14, 2025, FERC accepted Southwest Power Pool, Inc.’s (“SPP”) proposed revisions to its Open Access Transmission Tariff (“OATT”) to modify its high priority transmission study planning process. SPP argued these changes...more
On April 11, 2025, FERC issued Order No. 1920-B, which clarified and maintained key requirements from Order No. 1920-A regarding long-term transmission planning and cost allocation. FERC clarified that transmission providers...more
At its latest open meeting on February 20, 2025, the Federal Energy Regulatory Commission (FERC) issued an order directing PJM Interconnection, L.L.C. (PJM) and the PJM Transmission Owners (PJM TOs) to demonstrate why the PJM...more
On January 16, 2025, FERC approved a contested settlement agreement and rate schedule governing the provision of reliability must-run (“RMR”) service from the Indian River Unit 4 generating facility (“Unit 4”) in PJM...more
The Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Office of Enforcement (“Enforcement”) continues to focus on enforcing its duty of candor rules, with a recent action resulting in a $6.6 million civil...more